Gem Pier Repairs

Project duration & key dates

Works commence - April 2020
Works complete – June 2020

Stage One – wrapping and repairing piles by diver - complete
Stage Two – replacing damaged piles by barge

Project funding

$650,000

Project partners

Department of Transport - Better Recreational Facilities program

Key information

Works will include wrapping and repairing damaged piles where possible and replacing other piles. Works are anticipated to take approximately eight weeks, weather dependent.

Access restrictions
Access to the commercial lower landing for ferries will remain open.
The pier will be restricted at times during second phase works.

Signage will be on site advising the public of access closures.

Other information

An important pier in Victoria’s maritime history, Gem Pier was named after the steamboat Gem ferry service that ran between Williamstown and Port Melbourne.

 

X
By using our site you accept that we use and share cookies and similar technologies with certain approved third parties. These tools enable us to improve your website experience and to provide content and ads tailored to your interests. By continuing to use our site you consent to this. Please see our Privacy Policy for more information.