Buchan Caves Reserve Flood and Fire Recovery
The Buchan Caves Reserve is one of 14 joint-managed parks across Gippsland. Parks Victoria recognise the Gunaikurnai Traditional Owners holds Native Title and an intrinsic connection to Country.
We are working in partnership to deliver memorable visitor experiences at the reserve.
Parks Victoria has a Joint Management Agreement with the Gunaikurnai Land and Waters Aboriginal Corporation (GLaWAC). The agreement recognises Parks Victoria and GLaWAC are:
- managing country together
- protecting cultural values
- promoting environmental conservation.
There is an approved Cultural Heritage Management Plan (CHMP) for the reserve.
Recovery projects
Black Summer bushfires 2019-2020
The 2019-20 Black Summer bushfires destroyed visitor facilities at the Buchan Caves Reserve.
Planning and construction works are ongoing to restore and upgrade:
- cabins and wilderness retreats
- Guide Hut
- lookouts and bridges
- day and camping visitor facilities
- walking tracks.
December 2023 flood
On Boxing Day 2023, the Buchan Caves Reserve experienced an extreme flooding event.
More than 60 millimetres of rain fell in 30 minutes. The flood caused major damage to buildings and bridges. The road network was also severely damaged. During the initial clean-up phase more than 250 tonnes of debris was cleared away.
Construction and planning for flood restoration works are ongoing on:
- Royal Caves entrance
- Visitor Centre and toilet block remediation
- heritage listed rotunda near the Fairy Caves entrance
- rock wall near the wastewater treatment plant.
Pictured: Final works on the new Yarning Circle were completed in November 2025
You can find out more and subscribe to Buchan Caves Reserve recovery projects updates below.
Buchan Caves Reserve flood Dec 2023
Last updated: November 2025
Ongoing works
Buchan Caves Reserve is open to visitors as work continues on key recovery projects. We are working on new and restored facilities for visitors to enjoy.
During the works, the reserve is open daily for bush walks, camping, day picnic spots and relaxing in nature.Construction works recently completed or underway, include:
- new Yarning Circle opened to visitors in November 2025
- Spring Creek Track completed two months ahead of schedule in October 2025
- Guild Hit rebuild contract was awarded with works expected to start soon
- Visitor Centre has ongoing works to repair flood damage
- entry gate sculpture designs and approvals are underway
- design for the heritage-listed rotunda has been completed
We apologise for any inconvenience during the construction and recovery works.
Temporary Visitor Centre open during works
Visitors can buy tickets and retails goods at the temporary office for reserve activities including the Royal and Fairy Caves tours. Starting in July 2025, the Visitor Centre works are remediating impacts from the 2023 Boxing Day flood.
Roofed accommodation
Planning and design works continue for roofed accommodation options to enable visitors to enjoy year-round heating and cooling, hot showers, drinking water and kitchen facilities.
North Arm flood mitigation
Works to reduce flooding and deliver a safer visitor experience are in progress and expected to be completed by late-September 2025. During the works, a swale drain was built on the eastern side of the North Arm. The project will see surface water runoff diverted into Spring Creek during heavy rainfall, reducing the potential impacts of flooding in the North Arm.
Yarning Circle and entry gateway sculpture
Construction is almost complete on the Yarning Circle cultural and education space. The circle will open to visitors when the plantings are established. Designs and approvals are progressing on the entry sculpture which will welcome visitors to the Buchan Caves Reserves.
These projects are being led by GLaWAC who have developed the designs and are currently completing the Yarning Circle installation, The entry gateway sculpture is at the approvals stage and works will start when all permits are received.
When completed, the Yarning Circle will offer visitors a place to learn about the local Gunaikurnai culture and connect with each other.
Spring Creek Track now open
GLaWAC work crews have replaced the fire-damaged structures along the walking track. The recovery works were completed two months ahead of schedule.
The works will see visitors enjoying access to:
- restored pedestrian bridge
- new viewing platform
- upgraded steps and path edging
- new handrails to support walkers along the track.
For visitor safety the track was closed during the works. Construction was completed in October 2025 in time for the busy visitor season from late spring into early autumn.
Royal Cave entrance tunnel
The entrance tunnel to the Royal Cave was damaged in the Boxing Day 2023 flood. An engineer has assessed the damage and is providing recommendations on the remediation and design needed to safely re-open the entrance.
Guide Hut rebuild
Following the Boxing Day 2023 flood, a flood modelling assessment was completed to inform future works. In response to this assessment, the existing designs for the Guide Hut have been amended to make the new building more resilient to flood. Permits have been received for the revised design, and procurement is underway.
Heritage and Linaker tree replanting
A significant collection of specimen trees, which were part of a planting scheme developed in the 1920s by landscape designer Hugh Linaker, were lost in the drought, bushfire, and floods. Heritage Act approvals have been submitted. Planning for the replanting program has started, tree planting will begin when all permits and approvals are received.
Project timelines
The following timelines are subject to assessments, permits, procurement, and on-ground and construction industry conditions. Timelines are currently under review following flood impacts and will be updated here as each projects progresses.
Campground reopens: From the September school holidays the Buchan Caves Reserve campground returned to normal service. We had temporary closures of some campsites in the North Arm campground to keep visitors safe during recovery works.
Visitor Centre: Visitors can buy tickets for caves tours, and other retail items from our temporary visitor centre and office. Works to repair impacts of the Boxing Day flood are underway. We are working to have some parts of the buildings completed and ready for the peak 2025/26 summer season. Works are expected to continue into 2026.
Heritage listed rotunda: The design for the repair of the rotunda has been completed. Pending approvals and permits construction works are expected to be completed by early 2026.
North Arm flood mitigation: Works are now complete.
Yarning Circle and entry gateway sculpture: Construction of the Yarning Circle started in August, and works were completed in November 2025. Construction of the entry sculpture will start when all permits and approvals are received.
Royal Cave entrance tunnel: Remediation design for the rebuild of the cave entrance is expected to be completed in late 2025. Construction will start when all assessment, permits and approvals are received.
Guide Hut rebuild: The contractor for the upgrade and rebuild of the Guide Hut has been appointed. Works are expected to start in late-2025. All approvals have been received with expected completion in mid-2026.
Roofed accommodation: Planning and design works are progressing for the roofed accommodation options. Upgrades will enable more visitors to enjoy year-round stays at the Buchan Caves Reserves.
Completed works
New Yarning Circle now open
Traditionally a place for First Nations collaborative decision making the Yarning Circle is now open. Works were completed in late October 2025 — some areas are currently fenced off to visitors to help the new plantings to establish.
North Arm flood mitigation
Works were completed on the eastern side of the North Arm in October 2025. A swale drain was built to divert surface water in to the Spring Creek. The upgrade will reduce the potential of flooding during rain events.
Spring Creek Track
Works started in July and were completed in October 2025.The works to reinstate fire damaged walking track facilities were reopened to visitors two months ahead of schedule.
Campground and Moon Hill track works
The walking trails are now open for bush walkers to enjoy. Remediation works on the walking tracks were completed in August 2025.
Caves Road bridge repairs
Repair works were completed in early 2025. The bridges had rock amor installed to improve visitor access and safety. The bridges along Caves Road were damaged in the Boxing Day flood. These works are now complete, and the bridges are open for all visitors.
Fairy Cave entrance
Visitors can now enjoy a covered waiting area and seating at the entrance to the reopened Fairy Cave tours. Thetimber log structure and roof of the Fairy Cave entrance were completed in March 2025. Visitors can now enjoy a covered waiting area and seating at the entrance to the reopened Fairy Cave tours.
FJ Wilson Walking Track repairs
In November 2024 with the track re-opened to visitors in time for the 2024/25 summer peak period. The FJ Wilson Track was damaged in the Boxing Day 2022 flood.
Environmental management
Buchan Caves Reserve supports significant wildlife populations, with Eastern Grey Kangaroos and Brush-tailed Possums often seen throughout the reserve. Over 100 species of birds have been recorded, with King Parrots, White-winged Choughs, and Currawongs listed as common. Bats are known to use some caves for overwintering and roosting. Platypuses inhabit the reserve’s waterways, using Moon Cave as an important breeding location. The reserve has a variety of native and introduced vegetation, including several species listed as threatened under the Flora and Fauna Guarantee Act 1988, such as Limestone Blue Wattle and Leafy Greenhood Orchid. The Linakar Tree Landscape Plan supports the heritage values of the reserve’s introduced plantings.
An application for a Flora and Fauna Guarantee Permit has been received. The permit will safeguard the native plants, animals and biodiversity within the reserve during on-ground works.
Putting safety first
Visitor safety is our number one priority when considering risk in parks. While nature will always be unpredictable, our projects and maintenance works help minimise risks and help people explore the great outdoors safely. At Buchan Caves Reserve and other flood-affected parks across the state, we're completing important assessments like flood modelling to determine how we can make our facilities and infrastructure more climate resilient into the future.
Parks Victoria is responsible for continuously managing and maintaining over 50,000 pieces of infrastructure across the state annually. We're also delivering new projects to help visitors get into nature. These are thoroughly planned and prepared to keep people and projects separate and safe.
When visiting a park where projects are happening, especially during construction, it's important that people follow the direction of signs, stay out of fenced and restricted areas, and listen to Parks Victoria staff and work crews.
Who we're working with
Parks Victoria and GLaWAC are working with East Gippsland Shire Council, East Gippsland Catchment Management Authority, Heritage Victoria and the Department of Energy, Environment and Climate Action (DEECA).
Access changes
For more information about access to areas within Buchan Caves Reserve please visit Buchan Caves Reserve and check the change of conditions.
Project funding
$2.8 million has been provided by the Department of Jobs, Skills, Industry and Regions (DJSIR) and the Department of Energy, Environment and Climate Action (DEECA), as well as insurance funds. The total budget will be confirmed once insurable asset amounts have been agreed.
Other information
- For more information on what there is to see and do at Buchan Caves Reserve, and for further information on updated conditions, visit Buchan Caves Reserve.
- For other bushfire recovery updates visit Cape Conran Coastal Park and Croajingolong National Park.
- News: Fairy Cave works start
- News: Buchan Caves re-opens for Easter
- News: Contractors arrive at Buchan for flood assessments
- News: Recovery works underway at Buchan Caves Reserve
- News: Information session on bushfire recovery projects
- Community information session November 2023: Recording
- Community information session November 2023: Presentation [PDF]
- Community information session November 2023: Questions and Answers [PDF]